Directs the Federal Energy Regulatory Commission, upon the request of a specified licensee, to extend for a maximum of three consecutive two-year periods the time required for commencement of construction of the AuSable Hydroelectric Project in New York.
[Congressional Bills 104th Congress]
[From the U.S. Government Printing Office]
[H.R. 4177 Introduced in House (IH)]
104th CONGRESS
2d Session
H. R. 4177
To extend the deadline under the Federal Power Act applicable to the
construction of the AuSable Hydroelectric Project in New York, and for
other purposes.
_______________________________________________________________________
IN THE HOUSE OF REPRESENTATIVES
September 25, 1996
Mr. McHugh introduced the following bill; which was referred to the
Committee on Commerce
_______________________________________________________________________
A BILL
To extend the deadline under the Federal Power Act applicable to the
construction of the AuSable Hydroelectric Project in New York, and for
other purposes.
Be it enacted by the Senate and House of Representatives of the
United States of America in Congress assembled,
SECTION 1. EXTENSION OF DEADLINE.
(a) Project Numbered 10812.--Notwithstanding the time period
specified in section 13 of the Federal Power Act (16 U.S.C. 806) that
would otherwise apply to the Federal Energy Regulatory Commission
project numbered 10836-000NY, the Commission shall, at the request of
the licensee for the project, and after reasonable notice, in
accordance with the good faith, due diligence, and public interest
requirements of that section and the Commission's procedures under that
section, extend the time period during which the licensee is required
to commence the construction of the project, under the extension
described in subsection (b), for not more than 3 consecutive 2-year
periods.
(b) Effective Date.--This subsection shall take effect on the date
of the expiration of the extension of the period required for
commencement of construction of the project described in subsection (a)
that the Commission issued, prior to the date of enactment of this Act,
under section 13 of the Federal Power Act (16 U.S.C. 806).
<all>
Introduced in House
Introduced in House
Referred to the House Committee on Commerce.
Referred to the Subcommittee on Energy and Power.